Contracted by a private national developer, BCCG was selected to Design-Build a new speculative facility. BCCG executed its cost-efficient solution for warehouse and distribution facilities using load-bearing, tilt-up concrete panels and structural steel framing to construct the facility. The bay includes a 60’ speed bay and 50’ x 50’ bay spacing with 35 docks and a clear height of 28’.

Existing soil conditions were found to be unsuitable for construction due to a high plasticity of the soil. BCCG over-excavated the soil by blending it with suitably engineered composition and replaced the unstable soil. In addition, BCCG worked with the local utility company to relocate above-ground power lines before starting construction. The project was completed on a fast-track schedule in 9 months.