To bring the best value to American Tire Distributors (ATD) at the Casper, Wyoming location, BCCG was selected to bring cost saving solutions to the site.

Aligning with ATD’s National Rollout Program prototypical facility design, the warehouse features a 4,000-square-foot office and 17 dock positions with varying dock heights to meet ATD’s needs. One critical element required to satisfy ATD on this project was to complete construction within a pre-defined nine-month schedule.

BCCG did not disappoint in meeting ATD’s needs. Leveraging its relationships with a national steel fabricator, BCCG shipped steel from North Carolina, which contributed to significant project savings. The existing tight labor force challenge was resolved when the steel fabricator brought in erectors from Georgia and completed steel erection in only 8 days. BCCG successfully completed the project on a nine month fast-track schedule, including land acquisition.